Closing a school-led project
Before closing a project, the project manager must do a final inspection, get council sign-off and submit closing paperwork to us.
Do a final inspection
The school representative and members of the project control group (PCG) must do a final inspection of the completed works.
They must check and confirm that all areas are clean and tidy, and all construction work is complete.
Identify defects in construction works
If any work is found to be incomplete, or defects are identified during the final inspection, the contractor must fix it. The time allowed for this is called the 'defects liability period'. The length of time allowed for this is stated in the contract.
If more defects are found during the liability period, the contractor must fix them too.
The contractor doesn’t have to fix any defects found after the liability period, unless the items are covered by a warranty.
Complete final documentation
At the end of the project, you must send all final paperwork to us. We can then close the project and pay out the amount needed for the cost of the project.
Complete the following documentation and submit it electronically to your regional NZSPA mailbox:
- School-led Project Closing Form
- Invoice template or a school generated invoice for final balance
- All project-related invoices
- Final school building / other financial information, and if required:
- a final building update form
- updated site plans
- building and product warranties
- design documentation.
Regional NZSPA contact details
The project manager will complete the “School-led Project Closing Form” and the DFA must sign the form.
The board must keep these in the project file for the life of the building. They also need to maintain the building or product in accordance with the warranties.
Council sign-off
If the project required building consent, your council must issue a Code Compliance Certificate (CCC) before anyone can use the building.
An exception is if you have a Certificate for Public Use (CPU). This allows the board to use a finished part, or all of, the building temporarily until the CCC is issued. The CPU usually expires after 6 months.
Ending the contract
Contractors must leave when construction is complete. You can’t keep contractors on for a later project unless the work was included in the original tender and contract.